Survey tasks help you track surveys delivered to a participant. Each task shows the date it was created/assigned, the due date, and the status (incomplete, complete, or closed).
Table of Contents
Viewing Survey Tasks
To see a list of survey tasks:
- Go to the "Participants" tab of the project settings screen.
- Select a participant.
- Select the "Task List" tab.
Closing Survey Tasks
Survey tasks assigned to participants are open until either the participant completes them, or they are closed by a project coordinator. You can close incomplete surveys to prevent participants from responding with out-of-date information, or if you need to re-deliver an updated survey.
To close a task, you have two options:
- "Complete Task" will close the task and mark it as completed. A completed task will show up on the participant's task list with a "complete" indicator, as if they had done the task themselves.
- "Close Task" will close the task without marking it as completed. It will disappear from the task list.
Surveys can either be closed automatically using schedules or manually, by completing the following steps:
- Go to the "Participants" tab of the project settings screen.
- Select a participant.
- Select "Task List."
- Use the "Filter by Status" button to select only incomplete tasks.
- Select "Close Task" or "Complete Task" to close any incomplete surveys you choose.